Why Did the Completion Percentage Go Down?

New construction budgets turn renovation draws into a moving target. Here is why line items regress between inspections, and the scope of work format that fixes it.


Every renovation lender has taken this call. A borrower opens their latest inspection report and a line item that was 100% complete last month now reads 50%. They did not undo any work. Their contractor has been on site the whole time. So why did the number go backward?

The answer is almost never the inspector. It is the budget. Specifically, it is a renovation project being administered on a budget template built for ground up construction, and it is one of the most common and most avoidable sources of draw disputes in construction lending.

Read on to learn more and request a Scope of Work Template.


One line item, two accurate inspections, two different answers

Here is the scenario, drawn from real inspection files. A two story home is under renovation. The budget carries a single trade line: Drywall, $17,700. The plan calls for new drywall upstairs first, then demolition and new drywall downstairs.

At the first draw inspection, the second floor has brand new drywall, just installed. The first floor still has its existing drywall. The inspector observes drywall on both floors and reports the line 100% complete. The lender releases the full $17,700.

Four weeks later, the first floor has been demolished to the studs, exactly as the plan requires. Drywall now exists on one of two floors. The inspector reports 50%.

One line item · Two accurate inspections · Two contradictory results
Draw Inspection 1
Upstairs drywall just installed
2ND FLOOR New drywall installed 1ST FLOOR Existing drywall in place
100%
Reported complete
Draw Inspection 2
Downstairs demoed per plan
2ND FLOOR New drywall installed 1ST FLOOR Demoed to studs
50%
Reported complete
▼ 50 point regression
$17,700released after Inspection 1
$8,850work in place at Inspection 2
$8,850disbursed ahead of the collateral

Neither report is wrong. Both inspectors recorded exactly what was observable on site. The budget handed them an instruction that cannot be scored consistently on a renovation, so two accurate observations produced contradictory results. The borrower disputes the report. The lender questions the inspector. The inspector stands by the photos. Everyone is right, and the draw stalls anyway.

Now multiply that across tile, flooring, paint, and plumbing fixtures, every trade that exists in the home before demolition. The gap between funds released and work in place compounds with every draw.


The budget is the problem, not the inspector

A trade based budget works on a ground up build because its assumptions hold there. On a renovation, every one of them breaks:

The new construction budget assumesWhat happens on a renovation
The site starts at 0% complete.The site starts full of existing finishes that look complete to an inspector.
Progress only moves forward.Demolition removes visible work. Progress moves backward mid project by design.
Each trade appears once, in sequence.The same trade repeats across areas and phases, months apart.
The trade name defines the scope.“Drywall” says nothing about which floors, what quantity, or new versus existing work.

The costs are real. Funds released against existing finishes mean the remaining loan balance cannot cover the remaining cost to complete if the project stalls. Regression triggers disputes that delay every subsequent draw. Two competent inspectors can score the same site differently when the lines do not define what counts, so results never repeat. And a disbursement history that does not reconcile with inspection data is exactly what an auditor or investor reviewer flags first.

The fix: budget the scope of work, not the trades

A scope of work budget replaces trade categories with work items. Each line describes one task an inspector can verify by observation, so completion is a fact, not a judgment call. A well formed line has four parts:

Install new drywall, hang, tape, texture · First floor, approx. 2,400 SF ·$7,500

Action verb

Task + spec

Location + quantity

Value

Five rules that make it work

  • 1
    Give demolition its own lines. Demo is paid work, and it is the single largest source of regression when it hides inside a trade line. Scored on its own, tearing out a floor moves the project forward instead of backward.
  • 2
    Split lines by area when phasing differs. Second floor drywall and first floor drywall complete at different times. Two lines score cleanly. One line guarantees a moving target.
  • 3
    One line, one observable outcome. If an inspector cannot mark the line done or not done from what is visible on site, the line is too broad. Split it.
  • 4
    Existing work to remain never appears in the budget. If it is not in the scope, it earns no credit and can never distort a percentage.
  • 5
    Value each line at its contract cost. When line values match the contractor’s pricing, percent complete equals dollars earned, and eligible funding falls out of the inspection automatically.

The same drywall, rebuilt

Here is the scope from our example in both formats. Same work, same $17,700, entirely different behavior under inspection:

New construction format

24Drywall$17,700

Which floors? New or existing? Does demo count against it? Every inspection is an interpretation.

Scope of work format

24aDemo existing drywall, first floor$3,000
24bInstall new drywall, second floor, approx. 2,200 SF$7,200
24cInstall new drywall, first floor, approx. 2,400 SF$7,500

Three observable facts. Any inspector scores them the same way on any visit.

Run the same inspections against the rebuilt lines and watch what happens:

Inspection 1
41%
Second floor install complete. Existing first floor drywall earns nothing: it is not in the scope.
Inspection 2
58%
Demo complete. Tearing out the floor moves the project forward.
Inspection 3
100%
First floor install complete. The line closes and stays closed.
Forward only. Regression is structurally impossible.

What a good scope of work budget looks like

The pattern holds across a full project. Action verb, task, location, value, grouped by phase so the construction sequence and the draw schedule line up:

#Scope of workLocationValue
Phase 1 · Demolition and site prep
1Demo kitchen: remove cabinets, countertops, appliances; cap plumbing and electricalKitchen$2,800
2Demo existing drywall, approx. 2,400 SFFirst floor$3,000
3Remove existing carpet and vinyl flooring, all roomsFirst floor$1,900
4Debris haul off, dumpsters, dust barriers, floor protectionWhole site$1,400
Phase 1 subtotal$9,100
Phase 2 · Structural and rough trades
5Frame new wall opening with LVL header per planKitchen$2,600
6Plumbing rough in: relocate sink line, add island supply and drainKitchen$3,600
7Plumbing rough in: new double vanity and shower valveHall bath$2,900
8Electrical rough: 12 new circuits, 14 recessed cans, island feedFirst floor$4,800
9HVAC: extend supply ductwork, add 2 registers, relocate returnFirst floor$2,400
Phase 2 subtotal$16,300
Phase 3 · Insulation and drywall
10Insulate exterior walls at opened areas, R-15 battsFirst floor$1,600
11Install new drywall: hang, tape, texture, approx. 2,400 SFFirst floor$7,500
12Install new drywall: hang, tape, texture, approx. 2,200 SFSecond floor$7,200
Phase 3 subtotal$16,300
Phase 4 · Finishes
13Install shaker cabinets and quartz countertops per specKitchen$16,400
14Tile shower surround and bath floor, approx. 220 SFHall bath$3,800
15Install LVP flooring, approx. 2,400 SFFirst floor$8,200
16Interior paint: walls, ceilings, trim, 2 coatsWhole interior$6,400
17Set plumbing fixtures: sink, faucet, toilet, shower trimKitchen + bath$2,300
18Install light fixtures and trim devicesWhole interior$2,100
Phase 4 subtotal$39,200
Total renovation scope$80,900

Every line can be photographed and marked done or not done. No line requires the inspector to know what existed before the project began.

This is not a niche preference. Itemized work write ups are the established standard across renovation lending. FHA 203(k) requires one for every project. Fannie Mae HomeStyle renovation loans are administered from an itemized scope of work. Private renovation and bridge lenders run their draw programs the same way, for the same reason: the budget is the inspector’s instruction set, and percent complete only means something when each line defines what done looks like.

How Land Gorilla carries the structure

Land Gorilla’s budget tools are built for exactly this format. Three features do the heavy lifting:

Sub descriptions

Every budget line supports an additional text field that travels with the line to the inspection. The line stays scannable (“Install new drywall”) while the sub description carries “First floor, approx. 2,400 SF, hang, tape, texture.” The inspector sees the full instruction in the field, and reports stay easy to read.

Categories

Group budget lines by unit or structure so each reports its own progress. Separate the units on a multifamily project, or separate a main residence renovation from a new build ADU on the same loan. The ADU scores like the ground up build it is, the main residence scores as a renovation, and neither distorts the other’s percentages.

Multiple budgets per loan

A single loan can carry more than one budget, each with its own lines and its own progress. Separate trade contracts cleanly: the GC contract as one budget, a pool contract as another. Each contract tracks against its own scope and its own draw activity, and percent complete stays meaningful within each contract instead of blending across them.

Five questions before you accept a renovation budget

If the answer to any of these is no, send the budget back for restatement:

  • Does every line begin with an action verb: demo, install, replace, repair?
  • Is demolition broken out on its own lines, never bundled inside a trade?
  • Is a location specified wherever the same trade appears in more than one area?
  • Can an inspector mark each line done or not done without guessing what counts?
  • Is existing work to remain excluded from the budget entirely?

The new construction template is the right tool for exactly one job: new construction. Give renovations a budget that describes the work, and the moving target disappears. Inspections score consistently, progress only moves forward, and draws reconcile with the work in place, which is the whole point of ordering the inspection in the first place.

Running renovations on a new construction template?

Ready to Transform your construction Lending experience?

Request a Demo
Construction Loan Management Software Dashboard

Share via
Copy link
Privacy Overview
Land Gorilla

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.

Strictly Necessary Cookies

Strictly Necessary Cookie should be enabled at all times so that we can save your preferences for cookie settings.