Alabama Construction Lending Requirements

A lien claimant can dismantle and sell a severable improvement here, even ahead of your prior mortgage.

Reviewed April 18, 2026Last statutory change 2024 · Amendment to Ala. Code § 34-8-1Statutes and disclaimer

  • Priority over prior mortgageLien first on severable improvements

  • Statutory waiver formNot statutory

  • Notice of commencementNot recognized

  • Contractor licensingState license

  • Preliminary noticeSets the lien size

  • Retainage10% cap; 1–16 units by contract

What a construction lender needs to know about Alabama

Alabama splits priority, lien rights and retainage in two. A mortgage recorded before work begins takes priority over the land, but a mechanics lien can take absolute super-priority over the building itself — enforced by physically removing the structure. Retainage and prompt-payment rules cap commercial and large multi-family work but switch off entirely for residential projects of 16 units or fewer.

Whether a sub gave notice decides how big its lien is.

Alabama runs two tiers of sub-tier lien. A subcontractor or supplier that gives the owner written notice before furnishing anything gets a lien for the full contract price. One that does not is limited to whatever the owner still owed the general contractor when the notice of intent arrived.

So an early notice in your file is a warning; the absence of one is a cap on the exposure.

Notice before furnishing
Full price lien — the claimant’s entire contract.
No advance notice
Unpaid balance lien — limited to what the owner still owes the GC.

Severable improvements outrank you outright.

Recording before commencement gives your mortgage first position on the land. It does not protect a severable improvement. Where the building or improvement is an entirety and separable from the land — framing, HVAC, even a whole new structure — a mechanics lien has super-priority over your prior recorded mortgage.

A claimant foreclosing on a severable improvement can physically dismantle and sell it. Plan for that with title endorsements rather than recording dates.

You hold priority onThe land
Severable improvementLien has super-priority
Claimant’s remedyDismantle and sell the structure
Cover the gapTitle endorsements, each draw

No new retainage after the halfway mark.

On commercial and multi-family of 17 units or more, retainage is capped at 10% of work properly done — and once the project reaches 50% completion, no further retainage may be withheld from later progress payments. Release comes within 60 days of completion or substantial completion.

10% until halfway
Then nothing more may be held from subsequent payments.
Residential and 1 to 16 units are exempt
Homebuilders and small multi-family run on contract terms, as do contracts under $10,000.
Two licensing boards
General Contractors board at $100,000 commercial; Home Builders board above $10,000 residential. Subs need their own license above the same thresholds.

Advance waivers are enforceable here.

Alabama has no statute prohibiting waiver of lien rights in advance of performance, so a clearly drafted no-lien clause is generally valid. It is only as good as the drafting, since the intent to waive must be explicit.

Document the payment flow anyway with a draw-by-draw exchange on your own forms.

  • Conditional · current draw
  • Unconditional · previous draw

Thirty days to the contractor, seven to the subs.

The prompt payment act covers private commercial and large multi-family work, exempting residential of 16 units or fewer and any contract under $10,000. Where it applies, the owner pays within 30 days of a proper request unless the contract says otherwise, and the prime pays subs within 7 days of being paid, with 1% monthly interest and possible attorney’s fees on late money.

Owner pays contractor30 days
Contractor pays subs7 days
Late payment1% per month; fees may be awarded
Exempt16 units or fewer, under $10,000

Alabama Lien Law Overview

Alabama’s mechanics lien laws (Ala. Code § 35-11-210 et. seq.) are highly procedural and create a bifurcated system of lien rights for subcontractors and suppliers. The statutes apply to both residential and non-residential construction, but the Prompt Payment and Retainage laws contain massive exemptions for residential homebuilders and smaller multi-family projects.

The most critical distinction in Alabama lien law lies in the two tiers of subcontractor/supplier liens:

  1. “Full Price Lien”: If a subcontractor or supplier provides written notice to the owner before furnishing any materials, they secure a lien for the full price of their contract.
  2. “Unpaid Balance Lien”: If a sub-tier party fails to provide advanced notice, their lien rights are strictly limited to the unpaid balance the owner still owes the general contractor at the time the owner receives a formal Notice of Intent to Lien.

Mortgage Priority

Alabama operates under a unique, bifurcated priority framework that poses a severe risk to construction lenders. Priority is split between the “land” and the “improvements.”

Priority Over the Land: Under Ala. Code § 35-11-211(a), a construction mortgage holds first-lien priority over the land itself against all mechanics liens, provided the mortgage is recorded prior to the commencement of work.

The “Severable Improvements” Exception (Extreme Lender Risk): Under Ala. Code § 35-11-211(b), a mechanics lien holds absolute “super-priority” over a previously recorded mortgage specifically regarding the building or improvement itself, provided the improvement is an entirety and is “separable from the land” (e.g., framing, HVAC systems, or even an entirely new structure). If a lien claimant forecloses on a severable improvement, they possess the statutory right to physically dismantle, sell, and remove the building from the land to satisfy their claim, leapfrogging the lender’s first-position mortgage.

Priority of Progress Draws (Future Advances): In Alabama, the priority of subsequent progress draws depends heavily on whether the advances are “obligatory” or “optional” under the loan agreement and Ala. Code § 35-10-123. If the loan agreement makes advances optional, and the lender disburses funds after receiving actual knowledge of an intervening mechanics lien, those newly disbursed funds lose their first-lien priority. Therefore, the lender should ensure the loan agreement clearly defines advances as obligatory, or strictly halt funding upon notice of any lien.

To establish priority over the land, the construction mortgage MUST be recorded before any visible work begins (Ala. Code § 35-11-211(a)). However, because the lender cannot statutorily defeat the super-priority of a lien on severable improvements, securing specific title insurance endorsements is a crucial risk-mitigation strategy.

Retainage Overview

Alabama’s retainage regulations differentiate heavily based on the number of units being constructed.

Commercial & Multi-Family (17+ Units): Under Ala. Code § 8-29-3, retainage on private commercial and large multi-family projects is strictly capped. An owner MUST NOT withhold more than 10% of the estimated amount of work properly done (Ala. Code § 8-29-3(i)). Crucially, once the project reaches 50% completion, no further retainage may be withheld from subsequent progress payments (Ala. Code § 8-29-3(i)).

  • Release Timeline: The owner MUST release and pay the retainage no later than 60 days after the completion of the contractor’s work or substantial completion of the project, whichever occurs first (Ala. Code § 8-29-3(l)).

Residential & Small Multi-Family (1-16 Units) Exemption: Under Ala. Code § 8-29-7, residential homebuilders and improvements to real property intended for residential purposes consisting of 16 or fewer units are explicitly exempt from the state’s statutory retainage caps. On these projects, the percentage of retainage and release timelines are governed entirely by the private construction contract.

Escrow: Alabama does not statutorily mandate that private retainage be held in an interest-bearing escrow account.

Prompt Payment Act

The Alabama Prompt Payment Act (Ala. Code § 8-29-1 et. seq.) applies to private commercial and large multi-family projects, but explicitly exempts residential projects of 16 or fewer units and any contracts under $10,000 (Ala. Code § 8-29-7).

  • Owner to GC: For applicable projects, the owner MUST pay the general contractor within 30 days of receiving a proper pay request or invoice, unless the contract specifies otherwise (Ala. Code § 8-29-3(a)).
  • GC to Subcontractor: The prime contractor MUST pay subcontractors within 7 days of receiving payment from the owner (Ala. Code § 8-29-3(b)).
  • Penalties: Late payments accrue interest at a steep statutory penalty rate of 1% per month (12% annually) and the prevailing party may be awarded reasonable attorney’s fees (Ala. Code § 8-29-6).

Lender Impact: Draw administrators managing commercial loans should ensure draw processing occurs swiftly. Unwarranted lender delays that force the owner to breach the 30-day payment window directly trigger 12% interest penalties against the borrower.

Title Practices

Under Alabama law, state statutes do not mandate title companies to administer construction loan disbursements. Lender-managed disbursements (or third-party draw administration) represent the standard industry practice.

To maintain first lien priority, verifying title and monitoring for liens at each draw is the primary best practice. Construction lenders should objectively utilize one of three primary options to achieve this: (1) Lien monitoring subscription services, (2) Title updates (which check public records but provide no insurance), or (3) Title endorsements (which provide actual insurance to the lender).

Strategic Benefit of ALTA Endorsements: It is highly recommended that lenders utilize ALTA 32 (Construction Loan) and ALTA 33 (Disbursement) title endorsements in Alabama. Because Ala. Code § 35-11-211(b) grants mechanics liens absolute “super-priority” over severable improvements (allowing a claimant to remove the building from the land even if the mortgage was recorded first), utilizing these endorsements is the only way a lender can shift this catastrophic priority risk to the title insurer. Regardless of the method chosen, leveraging these tools to clear encumbrances and verify public filings prior to releasing every single draw is crucial to mitigating risk.

Lien Waivers

Alabama does not dictate or publish specific, fill-in-the-blank statutory forms for lien waivers.

Lien Waiver Summary

Because Alabama does not provide statutory lien waiver templates, their enforceability is governed by standard contract law.

  • Advance Waivers Permitted: Alabama has no specific statutory provision prohibiting the waiver of lien rights in advance of performance. So-called “no-lien” clauses in construction contracts are generally valid and enforceable, provided the terms clearly and explicitly express the intent of the parties to waive lien rights.
  • Best Practice: While advance waivers are enforceable, lenders should still rely on heavily vetted, custom waiver forms to document payment flow. It is recommended to enforce a strict draw-by-draw exchange using Conditional Waivers for the current draw amount (conditioned upon the clearance of funds) and Unconditional Waivers for previously funded draws to definitively prove that payment reached the claimant and extinguished the corresponding lien right.

Lien Waiver Notarization

Alabama law does not stipulate that lien waivers be notarized to be considered legally valid and effective.

Notices

Notice of Commencement (or similar like event)

Alabama does not utilize a recorded Notice of Commencement for private construction projects to establish project start dates or trigger lien filing timelines. Priority is determined strictly by the actual, physical commencement of work.

Preliminary Lien Notifications

Preliminary notices in Alabama dictate whether a sub-tier claimant receives a “Full Price Lien” or an “Unpaid Balance Lien.”

  • General Contractors: Not statutorily mandated to send preliminary notices.
  • Subcontractors & Suppliers (Full Price Lien): To secure a lien for the full price of their contract, the claimant MUST provide written notice to the owner before furnishing any materials to the site (Ala. Code § 35-11-210).
  • Subcontractors & Suppliers (Unpaid Balance Lien): If the claimant fails to send the advanced notice, they are not completely barred from filing a lien, but they are limited to an “Unpaid Balance Lien.” To enforce this, they MUST serve a formal Notice of Intent to Lien upon the owner before officially recording their verified statement of lien (Ala. Code § 35-11-218).

Notice of Completion (or similar like event)

Alabama does not utilize a statutory Notice of Completion to truncate or alter the deadline for contractors to file mechanics liens. The lien window is strictly driven by the individual claimant’s last date of furnishing.

Additional State-Specific Notices

Demand for List of Materialmen: Under Ala. Code § 35-11-219, an owner (or a lender acting as an agent) possesses the statutory right to demand a complete list of all materialmen, laborers, and employees who have furnished materials or labor to the project from the original contractor. If the contractor fails to provide this list, they statutorily forfeit their own mechanics lien rights. This is a highly recommended tool for lenders to proactively map the supply chain and uncover hidden subcontractors before final disbursements.

Bonding Off Liens (Transfer to Security): Under Ala. Code § 35-11-233, an owner or lender possesses the statutory right to transfer a mechanics lien from the real property to a surety bond. The bond MUST be executed in an amount equal to double the amount of the lien claimed (or in such amount as approved by the judge of probate) (Ala. Code § 35-11-233). It is highly recommended that a lender ensure the borrower executes this process if a lien is filed, because filing this bond statutorily releases the property from the lien, clears the title, and allows the lender to safely resume loan disbursements.

Document References

  • Notice to Owner (Before Furnishing): A preliminary notice served by a subcontractor or supplier to the owner before materials are delivered. It benefits the claimant by establishing a “Full Price Lien.” For the lender, receiving this notice indicates that the noticing party possesses full lien rights, and it is highly recommended the lender collect a lien waiver before funds are disbursed. (Ala. Code § 35-11-210).
  • Notice of Intent to Lien: A statutory warning notice that MUST be sent to the owner by sub-tier claimants prior to officially recording a lien for the unpaid balance (Ala. Code § 35-11-218). It provides the lender and owner a crucial window to trap funds and resolve the dispute.
  • Verified Statement of Lien: The formal, notarized document filed in the probate court to perfect the encumbrance against the property’s title. Original contractors MUST file within 6 months of their last work; journeymen/laborers within 30 days; and all other sub-tiers within 4 months (Ala. Code § 35-11-213 & § 35-11-215).
  • Demand for List of Materialmen: A written demand served on the GC forcing them to reveal the supply chain. While there is no rigid statutory form, the document typically looks like a formal, certified letter from the owner (or lender) to the General Contractor, explicitly citing Ala. Code § 35-11-219. To be effective, the document MUST explicitly demand a “complete list of all materialmen, laborers, and employees” who have furnished or are contracted to furnish materials or labor. Practically, it should be formatted to request a detailed schedule listing each sub-tier party’s name, contact information, scope of work, contract amount, and outstanding balance. It benefits the lender by identifying unknown parties. If the GC fails or refuses to respond to this written demand, they statutorily forfeit their own lien rights. (Ala. Code § 35-11-219).

Contractor Licensing & Bond Requirements

Alabama heavily regulates contractor licensing at the state level through two distinct boards based on the property type and project value.

  • Commercial & Public Works: The Alabama Licensing Board for General Contractors licenses contractors performing commercial, industrial, or public works where the cost of the undertaking (labor and materials) is $100,000 or more (Ala. Code § 34-8-1). For commercial swimming pool projects, the threshold is $5,000 or more (Ala. Code § 34-8-1(b)).
  • Residential Builders: The Home Builders Licensure Board (HBLB) licenses residential home builders performing construction or remodeling on residential structures (3 stories or less, 4 units or fewer) where the cost exceeds $10,000 (Ala. Code § 34-14A-2).
  • Subcontractors: Subcontractors working under a licensed prime contractor are REQUIRED by state law to hold their own state license if their specific portion of the work is $100,000 or more for commercial jobs (Ala. Code § 34-8-7) or exceeds $10,000 for residential jobs (Ala. Code § 34-14A-2(16)).
  • Surety Bonds & Specialized Trades: There is no blanket statewide surety bond mandate for general contractors, but applicants are statutorily expected to submit financial statements (CPA prepared) demonstrating a minimum net worth and working capital. Roofers taking residential jobs where the cost exceeds $2,500 are REQUIRED to be licensed as residential roofers (Ala. Code § 34-14A-2(16)).
  • License Lookup: Lenders should verify commercial credentials via the Alabama Licensing Board for General Contractors Portal and residential credentials via the Home Builders Licensure Board Portal.

Frequently Asked Questions

A framing subcontractor filed a lien on our project. We verified our mortgage was recorded weeks before any dirt was moved. Does our mortgage automatically have priority over the framer’s lien?

Not entirely. While your properly recorded mortgage holds first priority over the land, Alabama law (Ala. Code § 35-11-211(b)) grants the framing subcontractor absolute “super-priority” over the building or improvement if it is separable from the land. The framer could theoretically force the sale and removal of the structure to satisfy their debt. You should mitigate this extreme risk by requiring ALTA 32/33 title endorsements to shift the liability of severable improvements to the title insurer.

We are funding a commercial retail build. Our standard loan agreement dictates we withhold 10% retainage until the project receives its Certificate of Occupancy. Can we enforce this in Alabama?

No. Under Ala. Code § 8-29-3(i), private commercial retainage is strictly capped at 10% for the first half of the project. Once the project reaches 50% completion, no further retainage may be withheld from subsequent progress payments. Withholding a flat 10% through to the end of the project violates state law and exposes the owner to 1% monthly interest penalties.

A lumber supplier delivered materials to the job site last month and just sent the owner a preliminary notice yesterday. Will they be able to file a “Full Price Lien” if the GC fails to pay them?

No. To secure a Full Price Lien in Alabama, the supplier MUST notify the owner in writing before furnishing any material to the site (Ala. Code § 35-11-210). Because they sent the notice after delivery, they have lost their Full Price Lien rights. However, they can still file an “Unpaid Balance Lien” by serving a formal Notice of Intent to Lien before recording their verified statement, which limits their claim strictly to the funds the owner still owes the GC.

Statutes and disclaimer

State statute reference

Mechanics’ Liens
Code of Alabama § 35-11-210 et. seq.
Prompt Payment and Retainage
Ala. Code § 8-29-1 et. seq.
Last statutory change
2024 — Amendment to Ala. Code § 34-8-1: Raising the commercial general contractor licensing threshold to $100,000
Reviewed
April 18, 2026 by Land Gorilla

Disclaimer

Information on this website is provided for informational purposes only and is not intended to be legal advice or establish an attorney-client relationship. Construction law can change at any time, so the information on this website may not be the most up-to-date information available. The information on this website is posted “as is” and no representations are made that the content is without errors. Use of this website does not create an attorney-client relationship between Land Gorilla, content creators, law firms, and any other contributors to this website. Users of this website should contact their own legal counsel for advice with respect to any legal matters.